Project Experiences & Successes
BHP Billiton - Shenzi Waterflood Commissioning
GATE was involved early in the seawater treating design basis to influence / impart operability and commissioning efforts. From the design phase, GATE became responsible for dynamic commissioning and start-up during the offshore phase.
Shell - Ursa Princess Waterflood Commissioning
GATE provided seawater treating equipment process, materials, corrosion, chemical, and commissioning / start-up expertise. The scope included shaping the design of the seawater treating equipment and providing commissioning leadership and start-up expertise. The equipment included a Minox and Sulfate Removal Units.
Chevron - Tahiti II Waterflood
GATE provided process / commissioning expertise in the pre-commissioning and dynamic commissioning of the Tahiti II deaeration system (100,000 BWPD Minox).
Scope included planning for the offshore portion of the commissioning and offshore execution with the pre-commissioning contractor including confirmation of design, heat and mass balancing, and performance testing.