
Project Experiences & Successes
Slipline® - Pipeline Remediation Solution In LA Wetlands
A Louisiana operator experienced integrity issues with an existing 3 inch saltwater disposal pipeline. Production history recorded multiple leaks in the existing pipe, which resulted in environmental remediation. Upon investigation the operator determined that the said discharge pipe was unsuitable for future use. BlueFin was sought to review the situation and develop a plan of action that would resolve the integrity issues.
Remaining Life Assessment Of Subsea Jumpers, Flowlines & Risers
GATE was engaged to evaluate the current condition and remaining life of the subsea jumpers and flowline of a deepwater oil and gas facility in the Gulf of Mexico.
The subsea field, which was comprised of multiple oil wells, was produced at a Tension Leg Platform (TLP) with a nominal capacity to produce 100,000 barrels of oil and 50 million cubic feet of gas per day. The subsea and topsides facilities were designed to operate with an expected maximum carbon dioxide (CO2) concentration of 0.15 mole percent from any given producing well.
Post-IlI Corrosion Assessment & Wax Control Strategy
After an in-line inspection of a pipeline in West Africa, a client discovered significant wall loss in the first three miles of the line. The tool also returned significant wax deposits, casting doubt on the current wax management efforts in place.
The wells producing to the pipeline historically produced H2S; however, the worst offenders were shut-in quickly after it was discovered that they were producing extremely high concentrations of the sour gas.
Third Party Facilities Assessment
As part of a recent asset acquisition due diligence, GATE was asked to deliver a third party review of the condition of the asset and remaining production life of a floating production system and a fixed jacket.
GATE developed a standardized work process to evaluate the current condition, potential production bottlenecks and future operating expenditure (OPEX) associated with the brown-field producing asset.
Riser Life Extension Review
The review of the remaining cathodic protection (CP) life of a Gulf of Mexico tension-leg platform (TLP) was undertaken to evaluate the ability of the current systems to support a 20-year life extension. At the same time, the opportunity to include non-destructive riser testing into the life extension program was also identified.
Inspection Of Mill Certificates
During the fabrication of the subsea boarding valve skid for a major offshore platform in the Gulf of Mexico, the fabricator purchased several large forgings. These large forgings, from 8” to 12” in diameter, were to be machined into block valve bodies rated to 15,000 psig. As part of the agreed-upon Inspection and Test Plan, the mill certificates for the forgings were reviewed by the fabricator and by the company inspector.
Steam Plant Piping Corrosion
A steam generating plant supporting an associated thermal recovery project in the Middle East was experiencing through-wall corrosion of carbon steel lines. In some locations this was aggressive enough to corrode through replacement piping in as little as two months.
Comprehensive Flow Assurance Surveillance
Developed standalone tool for operator to proactively monitor flow assurance risks based on the field specific reservoir fluids, subsea infrastructure and current operating conditions.
Global, Comprehensive Materials, Corrosion & Integrity Support
A client operating domestically and internationally needed expert technical support for materials and corrosion control. Their senior management came to Viking for a proposal to provide a variety of consultancy services to cover the following essential needs: materials selection, failure analysis, corrosion monitoring, technical assurance for procurement, and risk assessment.
Well Integrity
We partnered with a major operator to develop and implement customized strategies to ensure well facility integrity by mitigating unforseen failures to maximize safety and uptime while minimizing cost.
Onshore Asset Integrity Management
GATE was consulted to identify the source of unexpected levels of H2S that had been detected in the central processing facility. Ultimately, GATE was able to determine that multiple operational issues needed to be addressed to mitigate the high levels of H2S in the processing facility, rather than the H2S naturally occurring in the reservoir.
Life Extension Study
A large and complex offshore field in the Middle East was suffering from multiple leaks due to corrosion in the presence of high levels of CO2 and H2S in the production, seawater injection, aquifer water injection and produced water injection systems. This was resulting in excessive chemical injection expenditures and was impacting field revenues and uptime. The large, shallow water field consisted of several hundred wells and a complex hub and spoke infrastructure.
Inspection Plan Development For Mothballed Equipment
A South American operator developed plans to return a sulfur recovery unit to service after an initial ten years of service and a further ten years of mothballing due to changes in field production requirements.
The corrosive nature of molten sulfur, carbon dioxide and hydrogen sulfide in the unit, coupled with the expectation of a less than optimum preservation strategy in a littoral offshore environment, generated a large set of integrity risks that needed to be evaluated to determine the feasibility of repairing and reinstating the system for a further ten years of service.
6-Inch Re-Assessment
A midstream company operating a high pressure gas pipeline required assessment services in order to maintain regulatory compliance. The said pipeline asset was considered unpiggable for ILI technology. In order to comply with regulatory guidelines for an MAOP verification, the company demanded a hydrostatic pressure test assessment.
Deepwater Flowline Dewater/Dry with High Pressure Nitrogen
An established operator in the Gulf of Mexico, through their preferred contractor, requested BlueFin to perform the dewatering of the flowlines for their two new tiebacks to an existing deepwater facility.
Pneumatic Pressure Test On Air Cooled Condenser (ACC) System
BlueFin Model A manifold systems are designed for high pressure, multiple line flushing and pressure testing.
Paraffin & Hydrate Remediation via eelReel
BlueFin Model A manifold systems are designed for high pressure, multiple line flushing and pressure testing.
Permian Operator Receives Integrated Expertise For Gathering System Commissioning
Planning and project management across a single source provide bundled solutions that deliver cost effective and schedule sensitive services for three separate Central Gathering Facilities (CGF’s) on an expedited timeline for first oil.
Hydrate Remediation Using Nitrogen
Provided complete hydrate blockage remediation support from initial onshore Engineering Assessment to execution planning and eventual successful field execution using nitrogen.
Hydrate Remediation
A Gulf of Mexico (GoM) operator in the process of decommissioning one of its fields requested the engineering assessment of a blockage existing in their flowline-riser. The reservoir fluid characteristics and the field’s operational history were extensively reviewed. The review indicated hydrates to be the likely cause of the blockage.