A GoM upstream operator experienced problematic pressure differentials. Over a period of time this resulted in heavy paraffin deposition and ultimately caused several pigs to become stuck in the 6” flowline. Upon an evaluation of available remediation methods, an extended reach mechanical solution was selected to remove the lodged pigs and properly remediate the paraffin deposition.
6”x18,000’ Cleanout via eelReel®
A Gulf of America operator experienced a blockage in a flowline which they suspected to be caused by recent pigging of the line. The blockage needed to be cleared before production could resume.
eelReel® Removes Stuck Pig & Paraffin
eelReel® successfully used to remove stuck pig and paraffin and restored production.
eelReel® Blockage Remediation For GOM Deepwater Flowline Decommissioning
A GoM operator of a 6-inch subsea oil production flowline experienced severe paraffin blockage. The said deposition prevented a successful hydrocarbon de-inventory procedure in order to properly abandon the asset per compliance regulations. Due to insufficient pump rates, the operator faced expensive, complex subsea intervention tasks based upon routine flow assurance methods typically applied in decommissioning scopes of work.
eelReel® Deepwater Riser Blockage Remediation On TLP
An operator of a mini-TLP experienced flow assurance problems in a subsea oil production flowline system. Operator knowledge and production history identified the issue as a paraffin blockage. Unsure of the blockage location and remediation method, several failed attempts at pressure cycling from the subsea and platform sides resulted in a mechanical remediation need.
eelReel® Unplugs 100% Paraffin Deposition
A GoM operator experienced problematic pressure differentials over a period of time, ultimately resulting in a completely plugged 6” flowline. Heavy paraffin solids completely plugged the flowline and prevented the transportation of liquid product. Upon an evaluation of available remediation methods, an extended reach mechanical solution was selected.
eelReel® Remediates 6” Offshore Pipeline
eelReel successfully used to remediate completely plugged 6” pipeline.
eelReel® - 6-Inch X 17,000 FT
A GoM upstream operator experienced problematic pressure differentials. Over a period of time this resulted in heavy paraffin deposition and ultimately caused several pigs to become stuck in the 6” flowline. Upon an evaluation of available remediation methods, an extended reach mechanical solution was selected to remove the lodged pigs and properly remediate the paraffin deposition.
Paraffin & Hydrate Remediation via eelReel
BlueFin Model A manifold systems are designed for high pressure, multiple line flushing and pressure testing.